Operations Research

Chapter 10 · Tamil Nadu State Board

  • 20 min read
  • 5-question quiz

Every key point below shows the sentence from your textbook it comes from. Book back answers are solved and checked against the book; answers we could not prove are left out. How we check content

In short

This lesson explains how Operations Research uses mathematical models to make better decisions when resources are limited. It teaches how to formulate a Linear Programming Problem and solve problems with two variables by using a graph and checking the feasible region’s corner points. It also introduces project networks, activity and event relationships, and rules for drawing and numbering a network. Critical Path Method calculations help identify the longest path and estimate the project completion time.

Written by AI from this lesson. How we check it

Key points

  • Operations Research applies scientific methods to complex problems involving large systems and resources.
    From your textbook
    “operations research is the application of scientific methods to complex problems arising from operations involving large system”
  • A Linear Programming Problem optimizes an objective function while respecting limitations on resources.
    From your textbook
    “used to optimize (maximize or minimize) the objective function with the limited resources.”
  • Formulating an LPP involves choosing decision variables, expressing the objective, and writing constraints.
    From your textbook
    “Identify the set of constraint conditions and express them as linear inequalities or equations in terms of the decision variables.”
  • For a two-variable LPP, the graphical method identifies the feasible region and compares the objective function at its corner points.
    From your textbook
    “By substituting these corner points in the objective function we can get the values of the objective function”
  • A project network arranges its activities logically and shows their relationships.
    From your textbook
    “Network is a diagrammatic representation of various activities concerning a project arranged in a logical manner.”
  • The Critical Path Method uses activity durations to identify the longest path and project completion time.
    From your textbook
    “The longest path connected by the activities in the network is called the critical path.”
Test yourself: 5 questions

Formulas in this chapter

  • General form of an LPPMaximize or Minimize Z = Σ c_j x_j; subject to Σ a_ij x_j ≤, ≥ or = b_i; x_j ≥ 0Explained here
  • Activity time calculationsEFT = EST + tij; LST = LFT – tijExplained here

Operations Research

Operations Research uses scientific methods to help solve complex problems involving people, machines, materials and money. It aims to make the best use of limited resources. An operations research model is an abstract or idealized representation of a real-life situation.

Models studied here

  • Linear programming problem
  • Network analysis

Remember: Operations Research helps choose a good plan when resources are limited.

Linear Programming Problem: Key Terms

Definition

Linear Programming Problem (LPP)
A mathematical technique used to maximize or minimize an objective function while working within limited resources.

Definition

Objective function
A function to be maximized or minimized, written as a linear function of the decision variables.

Definition

Decision variables
The variables whose values must be found to optimize the objective function.

Definition

Constraints
Linear inequalities or equations that express limits on the use of resources.

Definition

Feasible solution
A set of decision-variable values that satisfies every constraint and the non-negativity restrictions.

Definition

Optimal solution
A feasible solution that gives the maximum or minimum value of the objective function.

Definition

Feasible region
The common region satisfying all constraints, including the non-negativity restrictions.
General form of an LPP

Maximize or Minimize Z = Σ c_j x_j; subject to Σ a_ij x_j ≤, ≥ or = b_i; x_j ≥ 0

Z is the objective function; x_j are decision variables; c_j are their contributions to Z; a_ij are constraint coefficients; and b_i are resource limits or requirements.

How to Formulate an LPP

Formulation steps

  • Identify the decision variables.
  • Identify the objective and write it as a linear function of the decision variables.
  • Identify the constraints and write them as linear inequalities or equations.
  • Include non-negativity restrictions where the decision variables cannot be negative.

Choosing the constraint sign

SituationConstraint sign
At most or no more than a limit≤
At least a required amount≥
Exactly equal to an amount=

Remember: First decide what the variables represent. Then write the objective, resource constraints and non-negativity restrictions.

Worked LPP Formulations

Worked example

A furniture dealer buys tables and chairs. The investment limit is `10,000 and the storage limit is atmost 60 pieces. Each table costs ` 500 and gives a profit of ` 50. Each chair costs ` 200 and gives a profit of ` 15. Formulate an LPP to maximize profit.

Try it first, then show the solution
  1. Let x1 and x2 be the numbers of tables and chairs.
  2. The total profit is 50x1 + 15x2, so maximize Z = 50x1 + 15x2.
  3. The storage limit gives x1 + x2 ≤ 60.
  4. The investment limit gives 500x1 + 200x2 ≤ 10000, or 5x1 + 2x2 ≤ 100.
  5. The numbers of items cannot be negative, so x1, x2 ≥ 0.

Answer: Maximize Z = 50x1 + 15x2, subject to x1 + x2 ≤ 60, 5x1 + 2x2 ≤ 100, and x1, x2 ≥ 0.

Worked example

A company makes products P1, P2 and P3. Their profit contributions per unit are ` 20, ` 25 and ` 15. The man-hour requirements are 6, 3 and 12, with 200 available. The machine-hour requirements are 2, 5 and 4, with 350 available. The material requirements are 1kg, 2kg and 1kg, with 100kg available. Formulate an LPP.

Try it first, then show the solution
  1. Let x1, x2 and x3 be the units of P1, P2 and P3.
  2. The profit is 20x1 + 25x2 + 15x3, so maximize Z = 20x1 + 25x2 + 15x3.
  3. Man hours give 6x1 + 3x2 + 12x3 ≤ 200.
  4. Machine hours give 2x1 + 5x2 + 4x3 ≤ 350.
  5. Material gives x1 + 2x2 + x3 ≤ 100.
  6. Production quantities cannot be negative, so x1, x2, x3 ≥ 0.

Answer: Maximize Z = 20x1 + 25x2 + 15x3, subject to 6x1 + 3x2 + 12x3 ≤ 200, 2x1 + 5x2 + 4x3 ≤ 350, x1 + 2x2 + x3 ≤ 100, and x1, x2, x3 ≥ 0.

Worked example

A dietician mixes foods F1 and F2. Each kg of F1 costs ` 50 and contains 4 units of vitamin A and 6 units of vitamin B. Each kg of F2 costs ` 70 and contains 5 units of vitamin A and 3 units of vitamin B. The mixture must contain atleast 6 units of vitamin A and 9 units of vitamin B. Formulate an LPP to minimize cost.

Try it first, then show the solution
  1. Let x1 and x2 be the kg of F1 and F2.
  2. The cost is 50x1 + 70x2, so minimize Z = 50x1 + 70x2.
  3. The vitamin A requirement gives 4x1 + 5x2 ≥ 6.
  4. The vitamin B requirement gives 6x1 + 3x2 ≥ 9.
  5. The food quantities cannot be negative, so x1, x2 ≥ 0.

Answer: Minimize Z = 50x1 + 70x2, subject to 4x1 + 5x2 ≥ 6, 6x1 + 3x2 ≥ 9, and x1, x2 ≥ 0.

Formulating a Linear Programming Model

A linear programming model uses decision variables, an objective function, constraints, and non-negative restrictions. The objective function represents the quantity to maximize or minimize. The constraints make sure that available resources or required demand are respected.

Worked example

A firm makes S1, S2 and S3 at plants C1 and C2. Daily outputs are 3000 and 1000 bottles of S1, 1000 and 1000 of S2, and 2000 and 6000 of S3. April demand is 24000 bottles of S1, 16000 of S2 and 48000 of S3. Daily running costs are ` 600 for C1 and ` 400 for C2. Formulate a model that minimizes cost.

Try it first, then show the solution
  1. Let x1 be the number of days to run C1 and x2 be the number of days to run C2.
  2. The total running cost is Z = 600 x1 + 400 x2.
  3. Production must meet or exceed each demand: 3000 x1 + 1000 x2 ≥ 24000; 1000 x1 + 1000 x2 ≥ 16000; 2000 x1 + 6000 x2 ≥ 48000.
  4. The number of running days cannot be negative, so x1, x2 ≥ 0.

Answer: Minimize Z = 600 x1 + 400 x2, subject to 3000 x1 + 1000 x2 ≥ 24000, 1000 x1 + 1000 x2 ≥ 16000, 2000 x1 + 6000 x2 ≥ 48000, and x1, x2 ≥ 0.

Graphical Method for Two-Variable LPPs

The graphical method solves a linear programming problem with two decision variables. Draw the constraint lines and identify the feasible region, where all constraints hold together. The method is impractical for problems with three or more variables.

Steps in the graphical method

  • Write the problem mathematically.
  • Change each constraint into an equation and draw its line.
  • Find the feasible region.
  • Find the coordinates of each corner point.
  • Substitute each corner point into the objective function.
  • Choose the largest value for a maximization problem or the smallest value for a minimization problem.

Definition

Feasible region
The region containing points that satisfy all the constraints.

Definition

Corner point
A vertex of the feasible region, often found where two constraint lines meet.

Remember: For a graphical solution, compare the objective-function values at every corner point of the feasible region.

Maximization by the Graphical Method

Worked example

Maximize Z = 2 x1 + 5x2, subject to x1 + 4x2 ≤ 24, 3x1 + x2 ≤ 21, x1 + x2 ≤ 9, and x1, x2 ≥ 0.

Try it first, then show the solution
  1. Draw the constraint lines. Their intercepts are (0, 6) and (24, 0); (0, 21) and (7, 0); and (0, 9) and (9, 0).
  2. The feasible region has corner points O(0,0), A(7,0), B(6,3), C(4,5) and D(0,6).
  3. Evaluate Z at the corner points: O gives 0, A gives 14, B gives 27, C gives 33, and D gives 30.

Answer: The maximum value is Z = 33 at C(4,5). Thus x1 = 4 and x2 = 5.

Worked example

Maximize Z = 2 x1 + 3x2, subject to x1 + x2 ≤ 30, x2 ≤ 12, x1 ≤ 20, and x1, x2 ≥ 0.

Try it first, then show the solution
  1. The feasible region has corner points O(0,0), A(20,0), B(20,10), C(18,12) and D(0,12).
  2. Evaluate Z at these points: O gives 0, A gives 40, B gives 70, C gives 72, and D gives 36.

Answer: The maximum value is Z = 72 at C(18,12). Thus x1 = 18 and x2 = 12.

Minimization and No Feasible Solution

Worked example

Minimize z = 5x1 + 4x2, subject to 4x1 + x2 ≥ 40, 2x1 + 3x2 ≥ 90, and x1, x2 > 0.

Try it first, then show the solution
  1. Draw the lines 4x1 + x2 = 40 and 2x1 + 3x2 = 90. Their intercepts are (0,40), (10,0) and (0,30), (45,0).
  2. The feasible region has corner points A(45,0), B(3,28) and C(0,40).
  3. Evaluate z: A gives 225, B gives 127, and C gives 160.

Answer: The minimum value is z = 127 at B(3,28). Thus x1 = 3 and x2 = 28.

Worked example

Maximize Z = 2x1 + 3x2, subject to x1 − x2 < −1, −x1 + x2 < 0, and x1, x2 ≥ 0.

Try it first, then show the solution
  1. The conditions require points in the first quadrant that satisfy both inequalities.
  2. The two inequalities do not have a common feasible region.

Answer: There is no feasible solution, so the LPP has no solution.

How to select the optimum

Problem typeChoose at the corner point
MaximizationThe greatest objective-function value
MinimizationThe smallest objective-function value

Network Analysis and Project Activities

A project contains activities that must be done in a particular order. Some activities can start only after others are finished. Network scheduling shows these relationships and helps find the project completion time.

PERT and CPM

TechniqueUse described here
PERTA network-based planning and control technique for completing a planned schedule.
CPMA network-based planning and control technique, generally used when activity times can be determined exactly.

Definition

Activity
A task that uses time, effort, money or other resources, shown by an arrow from its starting event to its ending event.

Definition

Event
A point in time that marks the beginning or end of an activity and uses no resources.

Definition

Predecessor activity
An activity that must be completed before another activity can begin; A < B means B can start only after A is completed.

Definition

Successor activity
An activity that follows one or more activities and cannot start until they are completed.

Definition

Network
A diagram showing a project's activities arranged in a logical order.

Definition

Path
A set of nodes connected by lines from the network's initial node to its terminal node.

Definition

Dummy activity
An activity shown by a dotted line that uses no time or resources and only shows a technological dependence.

Constructing and Numbering a Network

Rules for drawing a network

  • Show each activity with one arrow. Only one activity can connect any two nodes.
  • Do not identify two activities by the same head and tail events.
  • Number nodes so each activity has a lower-numbered tail node and a higher-numbered head node.
  • Do not let arrows cross. Keep arrows straight, not curved or bent.
  • Every node must have an activity leading into it and an activity leading out, except the first and last nodes.

Rules for numbering events

  • Give each event a unique number.
  • Number events in sequence from left to right.
  • Number the initial event 0 or 1.
  • The head of an arrow must have a higher number than its tail.
  • Leave gaps in the sequence so activities can be added later if needed.

Remember: Numbering events according to these rules is called Fulkerson’s Rule.

Worked example

Activities C and D both follow A. E follows C, and F follows D. Both E and F must be completed before B.

Try it first, then show the solution
  1. Draw A before the branches leading to C and D.
  2. Place E after C and F after D.
  3. Bring both branches together before B.

Answer: The precedence order is A before C and D; C before E; D before F; and both E and F before B.

Worked example

The immediate predecessors are: A and B have none; C follows A; D follows B; E and F follow C and D; G follows E; H follows F.

Try it first, then show the solution
  1. Begin A and B without predecessors.
  2. Place C after A and D after B.
  3. Place E and F after both C and D.
  4. Place G after E and H after F.

Answer: The network must show A → C, B → D, C and D before E and F, E before G, and F before H.

Worked example

Activities A, B and C have no predecessors. D follows A; E follows B; F follows B; G follows C; H follows D; I follows F; J follows H and I; K follows F and G.

Try it first, then show the solution
  1. Start A, B and C independently.
  2. Place D after A, E and F after B, and G after C.
  3. Place H after D and I after F.
  4. Place J after both H and I, and K after both F and G.

Answer: The network must show the listed predecessor relationships. Use a dummy activity if needed to represent a dependence without adding time or resources.

Worked example

A < D, E; B, D < F; C < G; and B < H.

Try it first, then show the solution
  1. Place D and E after A.
  2. Place F after both B and D.
  3. Place G after C.
  4. Place H after B.

Answer: The network must show each activity after its stated predecessor or predecessors. A dummy activity may be used to show a dependence.

Critical Path Time Calculations

Definition

Ei
The earliest start time of event i.

Definition

Lj
The latest start time of event j.

Definition

tij
The duration of activity (i, j).

Forward pass

  • Start at the initial node with E1 = 0.
  • For an activity starting at node i, its earliest start time is ESij = Ei.
  • Find its earliest finish time using EFij = ESij + tij = Ei + tij.
  • At the next node j, use the greatest earliest finish time among its immediate predecessor activities: Ej = max EFij = max (Ei + tij).
  • At the final node n, the earliest project finish time is En = max EFij = max (Ei + tij).

Backward pass

  • Start at the final node n and set Ln = En.
  • For an activity ending at node j, its latest finish time is LFij = Lj.
  • Find its latest start time using LSij = LFij - tij = Lj - tij.
  • Move backward to node i and use the smallest latest start time among the activities leaving it: Li = min LSij = min (Lj - tij).
  • Continue until reaching the initial node.

Definition

Critical path
The path through the network with the longest total duration.

An activity (i, j) lies on the critical path when Ei = Li and Ej = Lj. It must also satisfy Ej - Ei = Lj - Li = tij. These conditions show that the activity fits the longest-duration path.

Finding activity times in a project network

EST is the earliest start time, and EFT is the earliest finish time. Add an activity’s duration to its starting event’s earliest time to find its EFT. For activities that reach the same event, use the smallest possible arrival time to find that event’s earliest time.

LFT is the latest finish time, and LST is the latest start time. Subtract an activity’s duration from its ending event’s latest time to find its LST. When finding an event’s latest time, use the largest value that fits the backward calculations.

Activity time calculations

EFT = EST + tij; LST = LFT – tij

tij is the duration of the activity from event i to event j. EST and EFT are its earliest start and finish times; LST and LFT are its latest start and finish times.

Forward and backward calculations

Forward calculationBackward calculation
Find earliest event times by moving through the network from the start.Find latest event times by moving backward through the network.
Choose the minimum arrival time when paths meet.Choose the maximum value when working backward from paths.

Critical path and project completion time

Definition

Critical path
The critical path is the longest path through the project network, formed by critical activities.

The activities on the critical path determine the project completion time. In the first example, the critical path is 1-2-4-5, and the project takes 21 days.

Worked project results

  • For the first project, the critical path is 1-2-4-5 and the completion time is 21 days.
  • In Example 10.14, the critical path is 1-2-4-6 and the completion time is 25 weeks.

Remember: The critical path is the longest path, and its duration gives the project completion time.

Activity time table for Example 10.14

The table gives the earliest and latest times for each activity in weeks. Read each row as activity, duration, EST, EFT, LST and LFT.

Activity times in weeks

  • 1-2: duration 8; EST 0; EFT 8; LST 0; LFT 8.
  • 1-3: duration 7; EST 0; EFT 7; LST 8; LFT 15.
  • 1-5: duration 12; EST 0; EFT 12; LST 9; LFT 21.
  • 2-3: duration 4; EST 8; EFT 12; LST 11; LFT 15.
  • 2-4: duration 10; EST 8; EFT 18; LST 8; LFT 18.
  • 3-4: duration 3; EST 12; EFT 15; LST 15; LFT 18.
  • 3-5: duration 5; EST 12; EFT 17; LST 16; LFT 21.
  • 3-6: duration 10; EST 12; EFT 22; LST 15; LFT 25.
  • 4-6: duration 7; EST 18; EFT 25; LST 18; LFT 25.
  • 5-6: duration 4; EST 17; EFT 21; LST 21; LFT 25.

Linear Programming Problem

Definition

Linear programming problem (LPP)
A mathematical method for using limited resources to maximize or minimize an objective function.

Definition

Objective function
A function that is to be maximized or minimized.

Definition

Decision variables
The variables whose values are chosen to optimize the objective function.

Definition

Solution
A set of decision-variable values that satisfies all the constraints.

Definition

Feasible solution
A solution that satisfies every constraint, including the non-negativity restrictions.

Definition

Feasible region
The common region that satisfies all constraints, including xj ≥ 0.

Definition

Optimal solution
A feasible solution that gives the maximum or minimum value of the objective function.

An LPP has an objective function and constraints. For problems with two variables, a graphical method can be used. The optimal value occurs at a corner point of the feasible region.

Remember: Check the corner points of the feasible region when finding the optimal value graphically.

Project Networks and Critical Path

Definition

Network
A diagram that arranges a project’s activities in a logical order.

Definition

Activity
A task or piece of work that uses time, effort, money or other resources.

Definition

Event
The beginning or ending point of an activity, also called a node.

Definition

Critical path
The longest path through the activities in a network, measured by its duration.

A project network shows how activities connect. Predecessor activities come before the activities that depend on them. The critical path takes the longest time and gives the project duration.

Project timing measures to calculate

  • Earliest start time
  • Earliest finish time
  • Latest start time
  • Latest finish time
  • Critical path
  • Project duration

Remember: The critical path is the longest-duration path through the project network.

Exponential Function Table

This table gives values of the exponential function for different decimal inputs. Find the row matching the decimal input, then use the column heading to find the required value. The column headings run from 0 to 9.

How to read the table

  • Choose the row for the given decimal value, such as 0.75.
  • Choose the column marked with the required number, from 0 to 9.
  • Read the value where that row and column meet.

Remember: Use the decimal input to select the row and the required column heading to select the table entry.

Questions students ask

Short, direct answers to what students search for in this chapter.

What is Operations Research?

Operations Research applies scientific methods to complex problems involving large systems of people, machines, materials and money. It helps decision-makers make the best use of limited resources in areas such as industry, business, government and defence.

What is a linear programming problem?

A Linear Programming Problem (LPP) is a mathematical technique for maximizing or minimizing an objective function when resources are limited. It uses decision variables, an objective function, constraints and non-negativity restrictions to describe the problem.

What are the steps to formulate an LPP?

First identify the decision variables. Next, express the objective to be maximized or minimized as a linear function of those variables. Then write the resource limits or requirements as linear inequalities or equations, and include non-negativity restrictions when the variables cannot be negative.

What is the difference between a feasible solution and an optimal solution?

A feasible solution satisfies every constraint and the non-negativity restrictions. An optimal solution is a feasible solution that gives the maximum or minimum value of the objective function. So every optimal solution is feasible, but a feasible solution is not necessarily optimal.

When do I use ≤ or ≥ in an LPP constraint?

Use ≤ when a quantity must not exceed a limit, such as an at-most storage capacity. Use ≥ when a quantity must meet or exceed a minimum requirement, such as atleast a specified vitamin amount. Use = when the quantity must be exactly equal to a stated amount.

How do you formulate a linear programming model?

Choose decision variables for the unknown quantities. Write an objective function to represent the quantity to maximize or minimize. Express each limitation or demand as a constraint, then include non-negative restrictions when the variables cannot be negative.

Show 16 more questions

What is the feasible region in a graphical linear programming problem?

The feasible region is the part of the graph where all the constraints hold at the same time. For two non-negative decision variables, it lies in the first quadrant. Its corner points are tested in the objective function to find the optimum.

How do you solve a two-variable LPP by the graphical method?

Turn each constraint into an equation and draw its line. Identify the region satisfying all constraints, then find its corner points. Substitute each corner point into the objective function. Select the greatest value for maximization or the smallest value for minimization.

What happens if the constraints have no common feasible region?

The LPP has no feasible solution. Without a common region, there are no values of the decision variables that satisfy all the constraints together, so there is no corner point to test for an optimum.

What is a dummy activity in network analysis?

A dummy activity shows a technological dependence between activities. It uses no time or resources and is represented by a dotted line. It helps show the correct relationships in a network without adding work or duration.

What is Fulkerson’s Rule?

Fulkerson’s Rule is the procedure for assigning numbers to events in a network. Event numbers must be unique and move from left to right. The initial event is numbered 0 or 1, and every arrow’s head node must have a higher number than its tail node.

How do you calculate earliest finish time in a network?

First find the earliest start time of the activity, which is the earliest occurrence time of its starting node. Add the activity duration: EFij = ESij + tij = Ei + tij. At a node with several predecessors, use the greatest predecessor finish time to find its earliest occurrence time.

What conditions show that an activity is on the critical path?

For activity (i, j) to lie on the critical path, the earliest and latest times must match at both ends: Ei = Li and Ej = Lj. The activity duration must also satisfy Ej - Ei = Lj - Li = tij.

What is the critical path in project network analysis?

The critical path is the longest path through a project network. It is made up of critical activities, and its duration determines the project completion time. For the first project shown, the critical path is 1-2-4-5.

How do you calculate the earliest finish time of an activity?

Add the activity’s duration to its earliest start time. The formula is EFT = EST + tij, where tij is the duration of the activity from event i to event j. For example, an activity with EST 8 and duration 10 has EFT 18.

How do you calculate the latest start time of an activity?

Subtract the activity’s duration from its latest finish time. The formula is LST = LFT – tij, where tij is the duration of the activity from event i to event j. This calculation is part of finding the latest times by working backward through the network.

What is the project completion time in Example 10.14?

The project completion time in Example 10.14 is 25 weeks. Its critical path is 1-2-4-6. The activities on this longest path determine the time needed to complete the project.

What is a feasible solution in linear programming?

A feasible solution is a set of values for the decision variables that satisfies every constraint in the problem. It must also satisfy the non-negativity restrictions on the variables.

What is the feasible region in an LPP?

The feasible region is the common region that satisfies all the constraints of a linear programming problem, including the non-negativity constraints xj ≥ 0. It is also called the solution region.

What is a critical path in a project network?

A critical path is the longest path through the activities in a project network. Its duration is the longest time needed along a path in the network, and the project duration is found from this path.

How do I use the exponential function table?

Find the row containing the given decimal input. Then locate the column with the required heading, from 0 to 9. The number where the selected row and column meet is the required table value.

What are the column headings in the exponential function table?

The column headings shown in the exponential function table are 0, 1, 2, 3, 4, 5, 6, 7, 8 and 9. Choose the heading that matches the value needed, then read across the corresponding row.

Book back answers

6 textbook exercises, solved and checked against the book. Questions we could not prove are left out.

Choose the correct answer

  1. In constructing the network which one of the following statement is false?

    • Each activity is represented by one and only one arrow. (i.e.) only one activity can connect any two nodes.
    • Two activities can be identified by the same head and tail events.
    • Nodes are numbered to identify an activity uniquely. Tail node (starting point) should be lower than the head node (end point) of an activity.
    • Arrows should not cross each other.
    Try it, then show the answer

    Two activities can be identified by the same head and tail events.

    The construction rules state that no two activities can be identified by the same head and tail events.

    From the book: “No two activities can be identified by the same head and tail events.”

  2. In a network while numbering the events which one of the following statement is false?

    • Event numbers should be unique.
    • Event numbering should be carried out on a sequential basis from left to right.
    • The initial event is numbered 0 or 1.
    • The head of an arrow should always bear a number lesser than the one assigned at the tail of the arrow.
    Try it, then show the answer

    The head of an arrow should always bear a number lesser than the one assigned at the tail of the arrow.

    The chapter's rule says the head of an arrow must have a higher number than its tail.

    From the book: “The head of an arrow should always bear a number higher than the one assigned at the tail of the arrow.”

  3. A solution which maximizes or minimizes the given LPP is called

    • a solution
    • a feasible solution
    • an optimal solution
    • none of these
    Try it, then show the answer

    an optimal solution

    An optimal solution is a feasible solution that maximizes or minimizes the objective function.

    From the book: “Any feasible solution which maximizes or minimizes the objective function is called an optimal solution.”

  4. Which of the following is not correct?

    • Objective that we aim to maximize or minimize
    • Constraints that we need to specify
    • Decision variables that we need to determine
    • Decision variables are to be unrestricted.
    Try it, then show the answer

    Decision variables are to be unrestricted.

    The chapter specifies non-negativity restrictions for decision variables in the LPP formulation.

    From the book: “A set of values of the decision variables that satisfies all the constraints of the problem and non-negativity restrictions is called a feasible solution of the problem.”

All 6 book back answers →

Practice

Question 1 of 5Score 0

What does an objective function represent in an LPP?

Exam questions

Practice questions with model answers. These are not from an official paper.

What is a Linear Programming Problem?2 marks

It is a mathematical technique used to maximize or minimize an objective function while working within limited resources.

State the main steps used to formulate a Linear Programming Problem.5 marks

Formulating a Linear Programming Problem (LPP) means expressing a decision-making problem mathematically so that an objective can be optimized subject to limitations.

  1. Identify decision variables: Define the unknown quantities to be determined using variables.
  2. Identify the objective: Decide whether the objective is to maximize or minimize, and express it as a linear function of the decision variables.
  3. Identify constraints: Determine the limitations on the use of resources or other conditions in the problem.
  4. Express the constraints mathematically: Write each constraint as a linear inequality or equation in terms of the decision variables.

Example: In the furniture-dealer example, x1 and x2 denote the numbers of tables and chairs; the objective is to maximize Z=50x1+15x2, subject to x1+x2≤60, 5x1+2x2≤100, and x1, x2≥0.

Thus, an LPP is formulated by defining the decision variables, objective function and constraints, together with non-negativity restrictions.

How is a two-variable LPP solved by the graphical method?5 marks

The graphical method is used to solve a linear programming problem involving only two variables. It determines the values of the decision variables that optimize the objective function while satisfying all constraints.

  1. State the problem: Write the objective function, constraints and non-negative restrictions mathematically.
  2. Draw the constraint lines: Replace each constraint inequality by an equation and draw the corresponding lines on a graph.
  3. Identify the feasible region: Find the common region that satisfies every constraint, including the non-negative restrictions.
  4. Find the corner points: Determine the coordinates of each vertex of the feasible region by inspection or by solving the equations of the intersecting lines.
  5. Evaluate the objective function: Substitute the coordinates of each corner point into the objective function and calculate its value.
  6. Select the optimum value: For a maximization problem, choose the greatest value obtained; for a minimization problem, choose the least value. The corresponding corner point gives the optimal values of the variables.

Example: In Example 10.5, the maximum value of Z = 2x1 + 5x2 occurs at C(4,5); hence x1 = 4, x2 = 5 and Zmax = 33.

Thus, the graphical method finds the optimal solution by comparing the objective-function values at the feasible region’s corner points.

What is the Critical Path Method, and what does the critical path indicate?2 marks

CPM is a network-based project technique. The critical path is the longest path of activities, and its duration gives the project completion time.

Watch out

  • Do not confuse a feasible solution, which satisfies the restrictions, with an optimal solution, which also maximizes or minimizes the objective function.
  • Do not treat an event as an activity: an event marks a point in time and does not consume resources.